The project consisted of the construction of a new roundabout, carriageway widening, footpath, street lighting landscaping, and drainage for the new Weldon Academy School.

Due to a delay in the 278 agreements being issued, the contract start date was delayed, which resulted in the programme being shortened.

The completion date, which aligned with the opening of the school, meant the programme could not be overrun.

We re-sequenced the programme, brought in additional resources and accelerated the programme to ensure that the completion date of the 5th September was met and the works were completed on time.